Overview
Heavy and highway labor from R&R Contracting on CSX's North Avenue bridge in Baltimore, part of the Howard Street Tunnel clearance program, 2024.
Baltimore, MD
Spiniello Companies for CSX Transportation
Summary
From July 15 to September 30, 2024, R&R Contracting's heavy and highway labor crews worked on CSX Transportation's North Avenue Bridge Modifications Project in Baltimore.
About the Project
The North Avenue work is part of CSX's Howard Street Tunnel clearance program, which opens the route for double-stack trains to and from the Port of Baltimore. The bridge's 19th-century masonry arches are being replaced.
R&R's Scope
Laborers, skilled laborers, operators and truck drivers.
Project Team
- Owner: CSX Transportation
- Contractor: Spiniello Companies
- Heavy and highway labor: R&R Contracting


Project Duration in Months
Workers Placed
Contract Value
Hillendale Park Community Water Main Replacement
Parkville, MD
Baltimore County's participation form names R&R Contracting as Cossentino Contracting's WBE subcontractor on the Hillendale Park water main replacement.

Certified Across Five States
R&R Contracting holds certifications that reflect our commitment to diversity and minority participation. These designations enable prime contractors to meet federal and local participation requirements on DOT-funded and government projects.