Fishing Point Submarine Cable Plant, Site Preparation

At the submarine cable plant Hellenic Cables America is building in South Baltimore, R&R Contracting laborers worked Allan Myers' site preparation contract.

Project Details

Overview

For Allan Myers, R&R Contracting laborers worked the site preparation contract at the Fishing Point submarine cable plant in South Baltimore.

Location

Baltimore, MD

Client

Allan Myers for Hellenic Cables America

Summary

Hellenic Cables America is building a plant in South Baltimore to make power, telecommunications and submarine cables, including cable for offshore wind. R&R Contracting provided laborers to Allan Myers on the site preparation contract for the plant, which the owner calls the Fishing Point Submarine Cable Manufacturing Facility. R&R's job is on record from September 2024 to February 2026.

About the Project

The roughly 38-acre site sits on the Patapsco River. The project received an Inflation Reduction Act Section 48C tax credit, which brings federal Davis-Bacon prevailing wage and apprenticeship requirements to the whole facility project, site preparation included.

R&R's Scope

General laborers, with certified payroll submitted to Allan Myers weekly.

Project Team

  • Owner: Hellenic Cables America
  • Contractor: Allan Myers
  • Laborers: R&R Contracting
Hellenic Cables logo
R&R Contracting construction crew
R&R Contracting construction crew
17

Project Duration in Months

Project Crew Size

Contract Value

Related Projects

Montebello Plant 2 Sediment Basins (WC-1396)

Baltimore, MD

R&R Contracting supplies Allan Myers with time-and-material crews and process piping on WC-1396, Baltimore's Montebello Plant 2 sediment basins.

Client
Allan Myers for the City of Baltimore
R&R Contracting construction crew
Certification

Certified Across Five States

R&R Contracting holds certifications that reflect our commitment to diversity and minority participation. These designations enable prime contractors to meet federal and local participation requirements on DOT-funded and government projects.

Let’s work together